We are the GC on a job we bid for the City. What types of rights do we have and monthly notice etc requirements. Thank you, Colbie @ ACIS Colbie.MacPhie@ACISinc.com
If you contracted directly with a city, then your rights are set out in your contract, and Chapter 2253 of the Texas Government Code and Chapter 271 of the Texas Local Government Code.
If you are a prime contractor, there are no monthly notice requirements.
Retain a construction attorney to evaluate your legal situation and to provide advice.
Good luck.