Is the deadline to file a lien for rented equipment the last day shipped or the last day returned?

New York
Sean Dwyer
Controller at Concrete Support Systems, LLC

We rent equipment for large poured in place concrete projects. The projects can last 6-12 months. I have been told the timeline to file a lien starts 8 months after the date of last shipment of equipment. However, since it is rental equipment and we retain ownership of the equipment and the potential length of the project, it seems the timeline to file a lien should start 8 months after the last return of equipment.

1 reply

It would depend on the terms of your contract. If your rental changes continue to run through the date the last equipment is returned, I think you're safe in calling that your last day of "work" for purposes of computing the deadline to file the lien. 

This response is supplied for informational purposes only and it is not intended to constitute legal advice. You should consult competent legal counsel
depending on the specific issues of your matter. See More...