We started this project on 11/29/21 is it too late to file a preliminary construction notice to the general contractor? we are the sub. We just submitted our first pay application last week. Thanks.
3 replies
Dec 30, 2021
It depends on where you are located. What State are you in?
0 people found this helpful
Helpful
Dec 30, 2021
Montana
0
Report Spam
Dec 30, 2021
You have 20 days after first supply of materials or labor. So looks like you are too late.