We are seeking clarification of when lien rights are lost in Nevada. 90 days after we worked on the site or 90 days after the last invoice date.

1 reply

Jul 25, 2018
Good question! In Nevada, the deadline to file a mechanics lien is the later of the following dates: (1) the completion of the work or improvement; or (2) the last furnishing of labor or materials by the lien claimant. Granted, if a Notice of Completion is filed, this 90-day period may be shortened to a mere 40 days.