Home>Levelset Community>Legal Help>In the State of Nevada, do we loose lien rights 90 days after last delivery or labor was done. Or is 90 days after the date of the last invoice?
In the State of Nevada, do we loose lien rights 90 days after last delivery or labor was done. Or is 90 days after the date of the last invoice?
Good question! In Nevada, the deadline to file a mechanics lien is the later of the following dates: (1) the completion of the work or improvement; or (2) the last furnishing of labor or materials by the lien claimant. Granted, if a Notice of Completion is filed, this 90-day period may be shortened to a mere 40 days.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...See More...