Residential remodel was performed in Oct 2019. Customer was satisfied with all the work perform excluding the flooring. Because of this we hired another contractor to refinish the floors to there satisfaction. When my company invoiced the remaining balance the customer responded that were not going to pay.

1 reply

Mar 30, 2021
You have three years from the date contract was breached, probably the date payment was due according to he terms of your contract, to file an action for breach of contract.