How long do we have to file a lien on property after work has been completed?
Generally speaking in Kansas, if you are a contractor, 120 days from date you last furnished supplies, material, equipment, or labor performed. If you are a subcontractor, 90 days from date you last furnished supplies, material, equipment, or labor performed.