Wee are a sub sub contractor on an airport project in MN (MAC) project. We did not file a prelim notice of intent to file a lien. Now contractor is refusing to pay us for extra work they told us to do. We have change orders submitted without their signing them - they just keep pushing forward and threatening us with delays if we dont work. How do I file a lien? Or get a copy of their bond? What do I do?