California

We filed the lien and the general contractor responded by sending a copy of the notice of completion, which was dated significantly before the date of the filing of the lien. We had not received this notice of completion previously.

1 reply

Jun 19, 2020
Assuming you served a preliminary notice in proper form and manner, you are entitled to be served with a notice of completion. If you were not, then the notice does NOT have the effect of reducing the time to record a lien from 90 days to 30 days
0 people found this helpful