Can we still file a Mechanics Lein after 60 days from doing work or suppling materials?

New JerseyMechanics LienPreliminary Notice

We subcontracted to work for a General Contractor at a residence. We keep getting told by the GC they have not gotten paid. We last were on-site September 10th, 2020 amid Covid-19 restrictions.

1 reply

May 24, 2021

 For residential construction a Notice of Unpaid Balance and Right to File Lien (NUB) must be filed within 60 days following the date the lien claimant last performed work or supplied services, material, or equipment to the residential real property for which payment is claimed. The lien claim must be filed no later than ten days following any arbitration decision or within 120 days following the last date the lien claimant performed work or provided services, materials, or equipment according to a written residential construction contract. 