Ive signed a conditional wiever for a company and now they tell me I have to wait 30 days to get payment. My 90 day mark to file lien is up on the 9th. I feel like they are doing this on purpose. What should I do. I sent a notice to file Lien and thats how we agreed on weiver
Typically the "conditional" part of a lien waiver is that the waiver is not valid unless and until they pay you the amount listed in the waiver. You should probably pursue your lien before time runs out.