I was working on a project in Breckenridge and after completing the project I have not been paid. It says I’ve missed a deadline?
Missed the deadline for what? To foreclose the lien or to serve and file the preliminary notice and lien?
A lot more information is nececessary. What was the work on the project. Is a lien necessary or not? What is the value?
Happy to help: this is my 30th year of practice and our firm has a specific practice area invovling lien and payment claims in construciton. Feel free to call or email for free consultation.
Jim
719-634-4200
Jim@coloradolawgroup.com
April 15th would be my last day and I have to send a notice of intent
Reach out to an attorney so they can get the facts and they will know exactly when you must serve and then file.
Robert Murillo
robert@pivotallegal.com.
I agree with my colleagues that more information is required. It's not clear whether liening is even in your best interest though. There are other potential avenues should you miss a deadline. Feel free to call our office to discuss. 7205007855.