What should I due if the lien deadline on a project was due 4-19-2021?
Unfortunately, it appears that you are out of time to file the mechanics' lien. In Pennsylvania, the six-month time limit begins on the date you last delivered labor and/or materials to the project. You do have other options available to you to collect , including suing the contractor. Please contact me if you would like to discuss or if you have any other questions. len@windishlaw.com, 215-979-7605