Can I file a Mechanics Lien?

CaliforniaRetainage
Iza Garcia
Agent at Paul Durham Electric, Inc

We are a Subcontractor for a large project, in the state of California. We finished the job last year. All previous invoices have been paid in full. We have the Retention invoice that has not been paid as of today. Can we put a Lien in this project?

2 replies

Construction Attorney at Brion Berkley, Attorney at Law
| 60 reviews
Apr 27, 2023

Depends upon if you submitted the "20-day preliminary notice" and if the project has passed the final inspection within the past 90 days. Asssuming the answer is "yes" to both those questions, and the property isn't owned by the government, then you probably can proceed with the Lien. However, it's always good to at least consult with a construction law attorney before recording a lien. 

1 person found this helpful
Helpful
Iza Garcia
Agent at Paul Durham Electric, Inc
Apr 27, 2023

Thank you Brion. 