I’m a subcontractor on a job where I have filed my unconditional and conditional waiver of release progress payments. Have not been paid for the month of February or March. Can I file a mechanics lien
Depends upon a few more factors, but assuming you served the preliminary notice, it's not a government project, project is finaled, and your stil within the 90 day window, then "yes." However, it is usually best to consult with an attorney to review everything before filing.
Brion Berkley, Esq.