We are a small business who started some work with a company back on 9/19 after received approval via email and via phone conversation. We want to ensure it is not too late file a mechanics lien. We started the work on 9/12, There were multiple projects. The last one we worked on was on 10/14 through 10/16. Can we still file a mechanics lien. We have sent a prelimnary and NOI previously.

2 replies

Feb 15, 2023

You can file a lien on the work you performed in October, but not September. Based on the 10/16 date you list above, I would get that lien filed today. Your time will run out tomorrow. You cannot file a lien for the work performed in September, though. If you need additional help, you can call my office at 918.770.4335, or send an email me to me at Jonathan@libertylegalok.com

1 person found this helpful
Helpful
Feb 15, 2023

I should also clarify that you only have 4 months to file that lien from the date the work is performed, etc. Again, if you have further questions, you can call my office at 918.770.4335, or email me at Jonathan@libertylegalok.com. Thank you!

1 person found this helpful