can a contractor hold out a subcontractors final payment in addition to retention?

Utah

Contractor is holding out subcontractors final billing in addition to a retention.

1 reply

Jan 12, 2021

It depends on what your agreement is. Frequently, contracts will permit the contractor to withhold enough to ensure that the work can be completed with the remaining funds. If the work is completed, then withholding more than retention would likely not be permitted. 