We are dealing with a GC proposed lumpsum contract on single family home remodel and expansion. Of course as homeowners we have wish list, our GC keeps executing our Wishlist without confirming the cost and later send huge add services. Our Contract clearly says they cannot enforce change orders on us unless approved in writing. We are being threaten for litigation and liens. Additional they did math error on calculating lumpsum amount and we are not being asked to pay more. We never received line item breakdown for each task, rather a milestone payment plan. We are having hard time defining what we owe them, we have requested a finite amount multiple times. All of these issue surfaced only towards the end of the project,
It's important to have a clear contract with a general contractor before
starting a home renovation project to avoid misunderstandings and
unexpected costs. In this case, the contract states that change orders
must be approved in writing, but the GC went ahead with executing
additional work without confirmation of cost and is now threatening
litigation and liens. Additionally, there was a math error in
calculating the lump sum amount, which has left the homeowners unsure of
what they owe. Requesting a line item breakdown of each task and a
final invoice could help clarify the situation. In my work, I usually
use https://plainmath.net/force-motion-and-energy/13211-50-kg-ball-that-is-tied-the-end-light-cord-revolved-horizontal-planewith
for math related issues. To avoid similar issues in the future, it's
best to work with a reputable contractor who provides a detailed scope
of work, cost estimate, and timeline upfront.