Last delivery of material 3/29, but customer is still on the job. We do not plan to deliver additional material, but the customer is still working on site with material we'd already delivered. The system is showing I have a lien deadline in 3 days - even if I put the completion date to June 2018. We absolutely need to maintain our rights. Do I need to file or not?