Menu
About Matthew Lakind
Matthew Lakind's practice focuses on construction law including construction defect litigation, Consumer Fraud Act claims, equitable adjustment/delay claims,
insurance issues related to construction, construction lien law, public bid protests, professional malpractice claims involving design professionals, and
negligence/tort claims arising out of construction projects. Mr. Lakind also drafts and negotiates contracts for a wide array of construction projects, including
large public and commercial projects, solar power installations under Master Service Agreements, and residential contracts.
More...
More...
Matthew Lakind's Recent Answers
Aug 24, 2020
From an Anonymous Contractor
New JerseyMechanics Lien
Material suppliers do have lien rights under New Jersey Law. A supplier must have a contract with subcontractor, the contractor, or the owner to qualify.
Essentially you need to be within the contractual chain. In your case, it sounds as if the contractor who purchased the material may be the owner of the
property, or it may be in contract with the owner. Under those scenarios you would qualify. Since this is a residential project that you supplied matSee More...
See More...
Jun 14, 2023
From an Anonymous Contractor
New Jersey
One option is to have the payment deposited to an attorney trust account if either of you have an attorney that would agree to do that. When an Owner
makes payment, the lien has been “satisfied” and can then be discharged. But before the payment is made, the lien is not considered satisfied.
See More...
Apr 22, 2023
From an Anonymous Contractor
New JerseyMechanics Lien
Unfortunately you cannot file a residential mechanic’s lien if more than 60 days have passed since your last date of work. Your right to file a breach of
contract claim/lawsuit against the GC remains. Also, depending on the nature of the homeowner’s promise to pay you directly, you may have a direct claim
against the homeowner beyond the expired lien rights. However, more information would be needed on that issue to make a full determination.
See More...
Mar 19, 2021
From an Anonymous Contractor
New Jersey
Unfortunately, you may be out of time to file the lien. Typically a lien must be filed 90 days from the last day of work on a commercial project. The clerks
offices have been filing liens as they come in. While there is some delay in the clerk's office in terms of getting them filed when they come in, it is likely that a
court would rule that you would’ve had to at least send the lien to the clerk for filing within the 90 days. With that said, you still have your rights to See More...
See More...
Mar 30, 2023
From an Anonymous Contractor
New Jersey
Typically unsigned change orders cannot be included in a lien. You may have lien rights, and also rights against any payment bond that may exist, in addition
to your breach of contract claims against the GC. More information is needed to fully assess the best options, however. This includes whether the project is
public or private, what your last date of work was, and what your contract says about withholding of payments, among other items.
See More...