Recent Questions & Answers About North Carolina Lien Waivers
At what point do we fill out the Waiver and release of liens(MLA appointed)?We are a subcontractor working at a project and received the waiver of release of liens(MLA appointment). We have submitted 1 pay application and have...
Conditional On Progress vs Unconditional on Parial PaymentMany of my projects are billed in 3 phases ( 60/40/10). Prior to the release of payment, I request that my contractor provides a conditional...
Why am I being asked to provide an executed lien waiverMay company has completed a job if removal of a burned historical building. We completedcthe job in Feb 2021. Since that time we have not...
Can a general contractor with hold payment due to not being able to provide a lien waiver from a supplier.We have completed a project for a commercial project. First payment was paid with no issues. Second payment was 21-30 days late depending on what...
Unconditional Lien LawsI am in the construction industry ( a construction monitor for lenders) I have been told that "In accordance with North Carolina statues, the Subcontractor...
Client is only offering to pay 10% of a projectI am trying to work with a client for a contracting job, half way through the job she wanted additional work for the same price....