General Contractor
Review the 65 Vaquero Construction Inc (CA) projects and payment history over the years. Know more about who you work with, how they pay, and avoid any potential issues on the job.
project
last
12 months
state
average
national
industrial average
Protected Projects
0%
41%
41%
Unprotected Projects
100%
54%
53%
Reported Slow Payment
0%
1%
2%
Projects With Liens
0%
4%
4%
Commercial Construction Project by D&H Construction at
Commercial Construction Project at
Construction Project at
1020 N Montebello Blvd, Montebello, CA 90640
Construction Project at
1030 N 4th St, San Jose, CA 95112
Construction Project at
29505 Mission Blvd, Hayward, CA 94544
Commercial Construction Project at
29497 Mission Blvd, Hayward, CA 94544
Construction Project at
613-669 VAN BUREN STREET, Gilroy, CA 95020
Construction Project at
133 E Oak St, Stockton, CA 95202
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
Residential Construction Project at
80 Blackburn St, Santa Cruz, CA 95060
Commercial Construction Project at
900 Sunset Dr, Hollister, CA 95023
Commercial Construction Project at
Commercial Construction Project at
16480 Del Monte Ave, Morgan Hill, CA 95037
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
Commercial Construction Project at
133 E Oak St 137, Stockton, CA 95202
Commercial Construction Project at
950 Main St 6941, Redwood City, CA 94063
Commercial Construction Project at
6800 Mission St 8376, Daly City, CA 94014
Commercial Construction Project at
1333 E Oak St, Stockton, CA 95205
Send an Invoice Reminder. Other contractors send an invoice reminder 15 and 25 days after sending an invoice.
Send a Notice of Intent to Lien to push for payment and avoid a mechanics lien. A notice of intent to lien results in payment on more than 95% of projects.
100% of projects in the last 12 months had no reported payment issues by other contractors.
Last 12 months - 100%
According to available information, 73% of projects in 2023 had no reported payment incidents.
2024 - 100%
2023 - 73%
2022 - 100%
2021 - 100%
Usually 10% retainage in California. See typical retainage by State for Vaquero Construction Inc (CA).
33% 5% retainage
67% 10% retainage
Typical contract pay terms not yet reported for Vaquero Construction Inc (CA).
Typical days to payment not yet collected for Vaquero Construction Inc (CA).