This page lists all the steps for subcontractors needed to work with The Dewitt Tilton Group. This includes how to get paid, the subcontractor prequalification process, finding open bidding opportunities, and the forms you should send on the job.
Dewitt Tilton Group Payment Process for Subs:
Subcontractors submit invoicing on or prior to the 20th of each month projecting to the 25th of each month.
The General Contractor (The Dewitt-Tilton Group) submits draw requests to Owners/Bankers by the 25th of each month.
At that time, a bank inspector will come out to be sure what the GC draws for has been completed.
Once the GC has been funded all Subcontractors are paid.
Dewitt Tilton pays their invoices faster than any General Contractor we do business with