Subcontractor
Review the 27 Sligar Mechanical LLC projects and payment history over the years. Know more about who you work with, how they pay, and avoid any potential issues on the job.
project
last
12 months
state
average
national
industrial average
Protected Projects
0%
34%
41%
Unprotected Projects
100%
59%
53%
Reported Slow Payment
0%
3%
2%
Projects With Liens
0%
4%
4%
State / County Construction Project by unknown general contractor at
901 S 13th St, Tecumseh, OK 74873
Commercial Construction Project by unknown general contractor at
410 W 7TH ST, Tulsa, OK 74119
Commercial Construction Project by Key Construction at
630 S JT STITES ST, Sallisaw, OK 74955
Commercial Construction Project by Cowen Construction at
7777 E 42nd Pl S, Tulsa, OK 74145
Commercial Construction Project by unknown general contractor at
603 W STONEWOOD DR, Broken Arrow, OK 74012
State / County Construction Project by unknown general contractor at
4200 SIX FORKS RD STE 1400, Muskogee, OK 74401
State / County Construction Project by unknown general contractor at
425 Boston St, Muskogee, OK 74401
Commercial Construction Project by unknown general contractor at
State / County Construction Project by unknown general contractor at
3600 Mohawk Blvd, Tulsa, OK 74115
Commercial Construction Project by Crossland Construction Company at
11601 S Garnett Rd, Broken Arrow, OK 74011
Commercial Construction Project by Manhattan Construction Group at
800 Altamont St, Muskogee, OK 74401
Commercial Construction Project by Cowen Construction at
14001 E 116TH ST N, Owasso, OK 74055
Commercial Construction Project by unknown general contractor at
Commercial Construction Project by Crossland Construction Company at
600 S Main St, Owasso, OK 74055
Commercial Construction Project by Manhattan Construction Group at
109 KERR AVE, Poteau, OK 74953
Commercial Construction Project by unknown general contractor at
1101 Honor Heights Dr, Muskogee, OK 74401
Commercial Construction Project by Piazza Construction (TX) at
Commercial Construction Project by Daris Contractors at
106 N 12th St, Collinsville, OK 74021
Commercial Construction Project by Crossland Construction Company at
Commercial Construction Project by Flintco, LLC at
12121 E 21st St S, Tulsa, OK 74128
State / County Construction Project by unknown general contractor at
Commercial Construction Project by Key Construction at
Federal Construction Project by unknown general contractor at
Send an Invoice Reminder. Other contractors send an invoice reminder 15 and 25 days after sending an invoice.
Send a Notice of Intent to Lien to push for payment and avoid a mechanics lien. A notice of intent to lien results in payment on more than 95% of projects.
100% of projects in the last 12 months had no reported payment issues by other contractors.
Last 12 months - 100%
According to available information, 100% of projects in 2023 had no reported payment incidents.
2024 - 100%
2023 - 100%
2022 - 50%
2021 - 100%
Typical retainage not yet submitted for Sligar Mechanical LLC.
Others typically said they were paid when paid from Sligar Mechanical LLC. See what were common payment terms.
100% Pay when paid
Sligar Mechanical LLC typically pays in < 15 days. This is self-reported by other contractors at the end of projects.
100% < 15 days