Subcontractor
Review the 71 DT Specialized Services projects and payment history over the years. Know more about who you work with, how they pay, and avoid any potential issues on the job.
project
last
12 months
state
average
national
industrial average
Protected Projects
0%
33%
41%
Unprotected Projects
100%
60%
54%
Reported Slow Payment
0%
3%
1%
Projects With Liens
0%
4%
4%
Commercial Construction Project by Miller-tippens Construction at
SE CORNER OF E 116TH ST N, Owasso, OK 74055
Commercial Construction Project by Flintco, LLC at
Commercial Construction Project by unknown general contractor at
Commercial Construction Project by unknown general contractor at
338242 EAST HIGHWAY 66, Chandler, OK 74834
Commercial Construction Project by unknown general contractor at
100 N Main St, Memphis, TN 38103
Federal Construction Project by unknown general contractor at
2727 S Rockford Rd E, Tulsa, OK 74114
Federal Construction Project by Commerce Construction Co. at
JOHN DAHL AVE, Pawhuska, OK 74056
Commercial Construction Project by unknown general contractor at
1506 E 46th St N, Tulsa, OK 74126
Commercial Construction Project by unknown general contractor at
550 S Peoria Ave E, Tulsa, OK 74120
Commercial Construction Project by unknown general contractor at
I44 W 9TH ST, Tulsa, OK 74127
Commercial Construction Project by Black Rock Construction Management LLC (OK) at
3000 N Hemlock Cir, Broken Arrow, OK 74012
Commercial Construction Project by Nabholz Construction at
909 W 23rd St S, Tulsa, OK 74107
Commercial Construction Project by unknown general contractor at
11200 E Pine St N, Tulsa, OK 74116
Commercial Construction Project by Nabholz Construction at
CORNER OF PRUDOM AVE HWY 60, Pawhuska, OK 74056
State / County Construction Project by Miller-tippens Construction at
111 N Cabaniss Ave, Bixby, OK 74008
Commercial Construction Project by Scott and Reid General Contractors at
11524 S Elwood Ave, Jenks, OK 74037
Residential Construction Project by unknown general contractor at
703 S Cherokee St, Catoosa, OK 74015
Commercial Construction Project by unknown general contractor at
2800 S 32nd St, Muskogee, OK 74401
Commercial Construction Project by unknown general contractor at
3817 S LEWIS AVE, Broken Arrow, OK 74013
Commercial Construction Project by Manhattan Construction Group at
Construction Project by unknown general contractor at
Construction Project by unknown general contractor at
3608 N Quaker Ave, Tulsa, OK 74106
Construction Project by unknown general contractor at
9898 S Memorial Dr E, Tulsa, OK 74133
Commercial Construction Project by Nabholz Construction at
1919 W 40th St S Ste CONTACT, Tulsa, OK 74107
Construction Project by unknown general contractor at
1543 N Greenwood Ave, Tulsa, OK 74106
Send an Invoice Reminder. Other contractors send an invoice reminder 15 and 25 days after sending an invoice.
Send a Notice of Intent to Lien to push for payment and avoid a mechanics lien. A notice of intent to lien results in payment on more than 95% of projects.
100% of projects in the last 12 months had no reported payment issues by other contractors.
Last 12 months - 100%
According to available information, 100% of projects in 2023 had no reported payment incidents.
2024 - 100%
2023 - 100%
2022 - 100%
2021 - 100%
Typical retainage not yet submitted for DT Specialized Services.
Typical contract pay terms not yet reported for DT Specialized Services.
Typical days to payment not yet collected for DT Specialized Services.