Levelset visitors can also get a free Procore account.

Georgia Bond Claim Guide and FAQs

File Your Georgia Bond Claim & Get Paid!

Get Your Lien Waiver Now
Georgia-Bond-Claims

Georgia Bond Claim Overview

Georgia

Preliminary Notice Deadlines
15 Days

Must file a Notice of Commencement within 15 days of beginning work.

Georgia

Bond Claim Deadlines
Prime contractors cannot file a claim against their own bond.

Georgia

Preliminary Notice Deadlines
30 Days

If a Notice of Commencement was properly filed by the prime contractor, sub-subs and suppliers not in contract with the prime contractor or public agency must give written Notice to the Contractor within 30 days of First Furnishing Labor and/or Materials to the project.

Georgia

Bond Claim Deadlines
90 Days

Must file notice of claim within 90 days from when you last furnished materials or supplies, and file a lawsuit to foreclose within 1 year from completion of entire public works project.

Georgia

Preliminary Notice Deadlines
30 Days

If a Notice of Commencement was properly filed by the prime contractor, sub-subs and suppliers not in contract with the prime contractor or public agency must give written Notice to the Contractor within 30 days of First Furnishing Labor and/or Materials to the project.

Georgia

Bond Claim Deadlines
90 Days

Must file notice of claim within 90 days from when you last furnished materials or supplies, and file a lawsuit to foreclose within 1 year from completion of entire public works project.

Georgia Bond Claim FAQs

Claim FAQs

Who is protected under Georgia Bond Claim Laws?

Georgia has relatively expansive protection for unpaid parties on public projects. In Georgia, parties who supply labor and/or materials to the general contractor, a subcontractor, a sub-subcontractor, or another supplier are protected and allowed to make a bond claim.

When is the deadline to file a Georgia Bond Claim?

A Georgia bond claim must be received within 90 days after the claimant’s last furnishing of labor and/or materials to the project. Note that delivery of notice of the bond claim is only specifically required when parties have no direct contract with the general contractor, and the general failed to comply with the notice of commencement requirements. Practically speaking, however, it is likely advisable for all parties in all circumstances to provide notice of the bond claim to start the process prior to initiating suit.

Who should receive the Georgia Bond Claim?

In Georgia, the bond claim must only be delivered to the general contractor. If the claimant wishes, a copy of the claim may also be sent to the surety (if known).

When is the deadline to initiate suit, or, how long is my Georgia Bond Claim effective?

In Georgia, suit must be initiated more than 90 days after the claimant’s last delivery of labor and/or materials to the project, but less than 1 year after the completion of the project as a whole.

What must the Georgia Bond Claim include?

In Georgia, a bond claim must only include the amount of the claim, and the name of the party to whom the labor and/or materials were furnished. It is likely advisable to also include the identification of the general contractor (if claimant hired by lower-tier party), and the contracting public entity, and include some description of the project and the labor and/or materials furnished.

What are the Lien Waiver Rules?

Georgia statutorily mandates that all parties on a construction project use certain legislatively designed construction lien waiver forms. This state is one of only 11 states that requires this. If a contractor or owner asks you to use a lien waiver form that does not conform to the statutory form, the waiver will be invalid, and the contractor could get in legal trouble. See this article: The 11 States with Statutory Lien Waiver Forms.

Also, Georgia state law prohibits contractors and suppliers from waiving their right to file a mechanics lien in contract. You can learn more about the prohibition of such “no lien clauses” at this article: Where Can You Waive Your Lien Rights Before Payment?

Can suppliers to suppliers file Bond Claims?

Yes, suppliers to suppliers likely have bond claim rights in Georgia.

How must the Georgia Bond Claim be sent?

The claim may be sent via registered or certified mail, or by personal service or other manner acceptable for service of process.

Need More Help with Georgia Bond Claims? We're Here.

Recent Questions & Answers About Georgia Claims

Can a property owner bond out of a lien placed against his property due to a subcontractor?

We placed a lien for $20K on a property that a subcontractor hired was hired to work on. The owner of the property says he...

Do we have 90 days from furnishing the last material to a project to file a claim on a bond?

We are a supplier for a prime contractor for a bonded public project in Georgia. The Miller Act states that if you have privity with...

Law firms that will take a case on a small retainer.or pro bono.

Is their any law firms that will take a case on a small retainer fee against a general contracter hired for a GA Dept of...

How to file a lien in Georgia

Need to file a Georgia mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.

Want to Learn More about How Georgia Contractors Pay?
Progress Residential
Rating 5.0
FirstKey Homes
Rating 5.0
Zillow Group Inc.
Rating 5.0
Dick's Sporting Goods
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Georgia Bond Claim Free Forms

Notice of Intent to Make Bond Claim Form - free from

Notice of Intent to Make Bond Claim Form

A Notice of Intent to Make Bond Claim is not a required document, but it can be a powerful one. By sending this notice, a...

Get Form Now

Georgia Bond Claim Statutes

When you perform work on a state construction project in Georgia, and are not paid, you can file a “lien” against the project pursuant to Georgia’s Little Miller Act. Since the claim is not against the state or county’s actual property, but instead against a posted bond, the claim is not really called a “lien” but is more frequently referred to as a “bond claim” or “little miller act claim.”

Georgia’s Little Miller Act is found in Georgia Code, Title 13, Chapter 10, §13-10-1, 2 and §13-10-40 – §13-10-65, and also Title 36, Chapter 91, §36-91-1, §36-91-2, §36-91-50, §36-91-70 – §36-91-95, and §36-91-110 – §36-91-119, and is reproduced below.

Georgia Code, Title 13. Contracts for Public Works

PART 1. BONDS

See below.

§ 13-10-1. "State" defined

As used in this article, the term “state” means the state of Georgia, any agency of the state, and any state authority.

§ 13-10-2. Approval of bond; strengthening of bond

(a)(1) Any bid bond, performance bond, payment bond, or security deposit required for a state public works construction contract shall be approved and filed with the treasurer or the person performing the duties usually performed by a treasurer of the obligee named in such bond. At the option of the state, if the surety named in the bond is other than a surety company authorized by law to do business in this state pursuant to a current certificate of authority to transact surety business by the Commissioner of Insurance, such bond shall not be approved and filed unless such surety is on the United States Department of Treasury’s list of approved bond sureties.

(2) Any bid bond, performance bond, or payment bond required by this chapter shall be approved as to form and as to the solvency of the surety by an officer of the state or the agency or authority of the state negotiating the contract on behalf of the state. In the case of a bid bond, such approval shall be obtained prior to acceptance of the bid or proposal. In the case of a payment bond or a performance bond, such approval shall be obtained prior to the execution of the contract.

(b) Whenever, in the judgment of the obligee:

(1) Any surety on a bid, performance, or payment bond has become insolvent;

(2) Any corporate surety is no longer certified or approved by the Commissioner of Insurance to do business in the state; or

(3) For any cause there are no longer proper or sufficient sureties on any or all of the bonds,

the obligee may require the contractor to strengthen any or all of the bonds or to furnish a new or additional bond or bonds within ten days. Thereupon, if so ordered by the obligee, all work on the contract shall cease unless such new or additional bond or bonds are furnished. If such bond or bonds are not furnished within such time, the obligee may terminate the contract and complete the same as the agent of and at the expense of the contractor and his or her sureties.

PART 3. PERFORMANCE BONDS

See below.

§ 13-10-40. Large public works contracts; requirement for performance bond

Except as otherwise provided in Title 32, performance bonds shall be required for all state public works construction contracts with an estimated contract amount greater than $100,000.00; provided, however, that the state may require a performance bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a performance bond shall be valid for any purpose unless the contractor gives such performance bond. The performance bond shall be in the amount of at least the total amount payable by the terms of the contract and shall be increased as the contract amount is increased.

§ 13-10-41. Alternatives to performance bond

When the amount of the performance bond required under this article does not exceed $300,000.00, the state may, in its sole discretion, accept an irrevocable letter of credit by a bank or savings and loan association, as defined in Code Section 7-1-4, in the amount of and in lieu of the bond otherwise required under this article.

§ 13-10-42. Maintenance of action on performance bond by obligee

The obligee in any performance bond required to be given in accordance with this article shall be entitled to maintain an action thereon at any time upon any breach of such bond; provided, however, no action can be instituted on the bonds or security deposits after one year from the completion of the contract and the acceptance of the public work by the state.

PART 4. PAYMENT BONDS

See below.

§ 13-10-60. Large public works contracts; requirement for payment bonds

Except as otherwise provided in Title 32, payment bonds shall be required for all state public works construction contracts with an estimated contract amount greater than $100,000.00; provided, however, that the state may require a payment bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a payment bond shall be valid for any purpose unless the contractor gives such payment bond; provided, however, that in lieu of such payment bond, the state, in its discretion, may accept a cashier’s check, certified check, or cash for the use and protection of all subcontractors and all persons supplying labor, materials, machinery, and equipment in the prosecution of work provided in the contract. The payment bond or other security accepted in lieu of a payment bond shall be in the amount of at least the total amount payable by the terms of the initial contract and shall be increased if requested by the state as the contract amount is increased.

§ 13-10-61. Liability of contracting entity for failure to comply with article

If a payment bond or security deposit is not taken in the manner and form required in this article, the corporation or body for which work is done under the contract shall be liable to all subcontractors and to all persons supplying labor, materials, machinery, or equipment to the contractor or subcontractor thereunder for any loss resulting to them from such failure. No agreement, modification, or change in the contract, change in the work covered by the contract, or extension of time for the completion of the contract shall release the sureties of such payment bond.

§ 13-10-62. Notice of commencement

(a) The contractor furnishing the payment bond or security deposit shall post on the public works construction site and file with the clerk of the superior court in the county in which the site is located a notice of commencement no later than 15 days after the contractor physically commences work on the project and supply a copy of the notice of commencement to any subcontractor, materialman, or person who makes a written request of the contractor. Failure to supply a copy of the notice of commencement within ten calendar days of receipt of the written request from such subcontractor, materialman, or person shall render the provisions of paragraph (1) of subsection (a) of Code Section 13-10-63 inapplicable to such subcontractor, materialman, or person making the request. The notice of commencement shall include:

(1) The name, address, and telephone number of the contractor;

(2) The name and location of the public work being constructed or a general description of the improvement;

(3) The name and address of the state or the agency or authority of the state that is contracting for the public works construction;

(4) The name and address of the surety for the performance and payment bonds, if any; and

(5) The name and address of the holder of the security deposit provided, if any.

(b) The failure to file a notice of commencement shall render the notice to the contractor requirements of paragraph (2) of subsection (a) of Code Section 13-10-63 inapplicable.

(c) The clerk of the superior court shall file the notice of commencement within the records of that office and maintain an index separate from other real estate records or an index with the preliminary notices specified in subsection (a) of Code Section 44-14-361.3. Each such notice of commencement shall be indexed under the name of the state and the name of the contractor as contained in the notice of commencement.

§ 13-10-63. Pursuit of action by person entitled to protection of payment bond; liability of public entity

(a) Every person entitled to the protection of the payment bond or security deposit required to be given who has not been paid in full for labor or materials furnished in the prosecution of the work referred to in such bond or security deposit before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by such person or the material or equipment or machinery was furnished or supplied by such person for which such claim is made, or when he or she has completed his or her subcontract for which claim is made, shall have the right to bring an action on such payment bond or security deposit for the amount, or the balance thereof, unpaid at the time of the commencement of such action and to prosecute such action to final execution and judgment for the sum or sums due such person; provided, however, that:

(1) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has not complied with the notice of commencement requirements shall have the right of action upon the payment bond or security deposit upon giving written notice to the contractor within 90 days from the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was performed or done. The notice to the contractor may be served by registered or certified mail or statutory overnight delivery, postage prepaid, duly addressed to the contractor, at any place at which the contractor maintains an office or conducts his or her business or at his or her residence, by depositing such notice in any post office or branch post office or any letter box under the control of the United States Postal Service; alternatively, notice may be served in any manner in which the sheriffs of this state are authorized by law to serve summons or process; and

(2) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has complied with the notice of commencement requirements in accordance with subsection (a) of Code Section 13-10-62 shall have the right of action on the payment bond or security deposit, provided that such person shall, within 30 days from the filing of the notice of commencement or 30 days following the first delivery of labor, material, machinery, or equipment, whichever is later, give to the contractor a written notice setting forth:

(A) The name, address, and telephone number of the person providing labor, material, machinery, or equipment;

(B) The name and address of each person at whose instance the labor, material, machinery, or equipment is being furnished;

(C) The name and the location of the public works construction site; and

(D) A description of the labor, material, machinery, or equipment being provided and, if known, the contract price or anticipated value of the labor, material, machinery, or equipment to be provided or the amount claimed to be due, if any.

(b) Nothing contained in this Code section shall limit the right of action of a person entitled to the protection of the payment bond or security deposit required to be given pursuant to this article to the 90 day period following the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made.

(c) Every action instituted under this Code section shall be brought in the name of the claimant without making the state or the agency or authority of the state for which the work was done or was to be done a party to such action.

§ 13-10-64. Supplying copy of bond or security deposit agreement and contract; fees for certified copies

The official who has the custody of the bond or security deposit required by this article is authorized and directed to furnish to any person making application therefor a copy of the bond or security deposit agreement and the contract for which it was given, certified by the official who has custody of the bond or security deposit. With his or her application, such person shall also submit an affidavit that he or she has supplied labor or materials for such work and that payment therefor has not been made or that he or she is being sued on any such bond or security deposit. Such copy shall be primary evidence of the bond or security deposit and contract and shall be admitted in evidence without further proof. Applicants shall pay for such certified copies and such certified statements such fees as the official fixes to cover the cost of preparation thereof, provided that in no case shall the fee fixed exceed the fees which the clerks of the superior courts are permitted to charge for similar copies.

§ 13-10-65. Time for instituting action

No action can be instituted on the payment bonds or security deposits after one year from the completion of the contract and the acceptance of the public works construction by the proper public authorities. Every action instituted under this article shall be brought in the name of the claimant, without the state or the agency or authority of the state for which the work was done or was to be done being made a party thereto.

Georgia Code, Title 36, Local Government Provisions, Chapter 91, Public Works Bidding

ARTICLE 1. GENERAL PROVISIONS

See below.

§ 36-91-1. Short titles

This chapter shall be known and may be cited as the “Georgia Local Government Public Works Construction Law.”

§ 36-91-2. Definitions

(1) “Alternate bids” means the amount stated in the bid or proposal to be added to or deducted from the amount of the base bid or base proposal if the corresponding change in project scope or alternate materials or methods of construction is accepted.

(2) “Base bid” or “base proposal” means the amount of money stated in the bid or proposal as the sum for which the bidder or proposer offers to perform the work.

(3) “Bid bond” means a bond with good and sufficient surety or sureties for the faithful acceptance of the contract payable to, in favor of, and for the protection of the governmental entity for which the contract is to be awarded.

(4) “Change order” means an alteration, addition, or deduction from the original scope of work as defined by the contract documents to address changes or unforeseen conditions necessary for project completion.

(5) “Competitive sealed bidding” means a method of soliciting public works construction contracts whereby the award is based upon the lowest responsive, responsible bid in conformance with the provisions of subsection (b) of Code Section 36-91-21.

(6) “Competitive sealed proposals” means a method of soliciting public works contracts whereby the award is based upon criteria identified in a request for proposals in conformance with the provisions of subsection (c) of Code Section 36-91-21.

(7) “Emergency” means any situation resulting in imminent danger to the public health or safety or the loss of an essential governmental service.

(8) “Governing authority” means the official or group of officials responsible for governance of a governmental entity.

(9) “Governmental entity” means a county, municipal corporation, consolidated government, authority, board of education, or other public board, body, or commission but shall not include any authority, board, department, or commission of the state, or a public transportation agency as defined by Chapter 9 of Title 32.

(10) “Payment bond” means a bond with good and sufficient surety or sureties payable to the governmental entity for which the work is to be done and intended for the use and protection of all subcontractors and all persons supplying labor, materials, machinery, and equipment in the prosecution of the work provided for in the public works construction contract.

(11) “Performance bond” means a bond with good and sufficient surety or sureties for the faithful performance of the contract and to indemnify the governmental entity for any damages occasioned by a failure to perform the same within the prescribed time. Such bond shall be payable to, in favor of, and for the protection of the governmental entity for which the work is to be done.

(12) “Public works construction” means the building, altering, repairing, improving, or demolishing of any public structure or building or other public improvements of any kind to any public real property other than those projects covered by Chapter 4 of Title 32 or by Chapter 37 of Title 50. Such term does not include the routine operation, repair, or maintenance of existing structures, buildings, or real property, or any energy savings performance contract or any improvements or installations performed as part of an energy savings performance contract.

(13) “Responsible bidder” or “responsible offeror” means a person or entity that has the capability in all respects to perform fully and reliably the contract requirements

(14) “Responsive bidder” or “responsive offeror” means a person or entity that has submitted a bid or proposal that conforms in all material respects to the requirements set forth in the invitation for bids or request for proposals.

(15) “Scope of project” means the work required by the original contract documents and any subsequent change orders required or appropriate to accomplish the intent of the project as described in the bid documents.

(16) “Scope of work” means the work that is required by the contract documents.

(17) “Sole source” means those procurements made pursuant to a written determination by a governing authority that there is only one source for the required supply, service, or construction item.

ARTICLE 3. BONDS

See below.

§ 36-91-40. Approval and filing of bonds with treasurer

(a)  (1) Any bid bond, performance bond, payment bond, or security deposit required for a public works construction contract shall be approved and filed with the treasurer or the person performing the duties usually performed by a treasurer of the obligee named therein. At the option of the governmental entity, if the surety named in the bond is other than a surety company authorized by law to do business in this state pursuant to a current certificate of authority to transact surety business by the Commissioner of Insurance, such bond shall not be approved and filed unless such surety is on the United States Department of Treasury’s list of approved bond sureties.

(2) Any bid bond, performance bond, or payment bond required by this Code section shall be approved as to form and as to the solvency of the surety by an officer of the governmental entity negotiating the contract on behalf of the governmental entity. In the case of a bid bond, such approval shall be obtained prior to acceptance of the bid or proposal. In the case of payment bonds and performance bonds, such approval shall be obtained prior to the execution of the contract.

(b) Whenever, in the judgment of the obligee:

(1) Any surety on a bid, performance, or payment bond has become insolvent;

(2) Any corporate surety is no longer certified or approved by the Commissioner of Insurance to do business in the state; or

(3) For any cause there are no longer proper or sufficient sureties on any or all of the bonds,

the obligee may require the contractor to strengthen any or all of the bonds or to furnish a new or additional bond or bonds within ten days. Thereupon, if so ordered by the obligee, all work on the contract shall cease unless such new or additional bond or bonds are furnished. If such bond or bonds are not furnished within such time, the obligee may terminate the contract and complete the same as the agent of and at the expense of the contractor and his or her sureties.

PART 3. PERFORMANCE BONDS

See below.

§ 36-91-70. Requirement of performance bonds

Performance bonds shall be required for all public works construction contracts subject to the requirements of this chapter with an estimated contract amount greater than $100,000.00; provided, however, that a governmental entity may require a performance bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a performance bond shall be valid for any purpose unless the contractor shall give such performance bond. The performance bond shall be in the amount of at least the total amount payable by the terms of the contract and shall be increased as the contract amount is increased.

§ 36-91-71. Acceptable substitutes for bond

When the amount of the performance bond required under this article does not exceed $750,000.00, the governmental entity may, in its sole discretion, accept an irrevocable letter of credit by a bank or savings and loan association, as defined in Code Section 7-1-4, in the amount of and in lieu of the bond otherwise required under this article.

§ 36-91-72. Action on performance bond

The obligee in any performance bond required to be given in accordance with this article shall be entitled to maintain an action thereon at any time upon any breach of such bond; provided, however, no action can be instituted on the bonds or security deposits after one year from the completion of the contract and the acceptance of the public work by the governmental entity.

PART 4. PAYMENT BONDS

See below.

§ 36-91-90. Requirement for payment bonds

Payment bonds shall be required for all public works construction contracts subject to the requirements of this chapter with an estimated contract amount greater than $100,000.00; provided, however, that a governmental entity may require a payment bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a payment bond shall be valid for any purpose, unless the contractor shall give such payment bond; provided, however, that, in lieu of such payment bond, the governmental entity, in its discretion, may accept a cashier’s check, certified check, or cash for the use and protection of all subcontractors and all persons supplying labor, materials, machinery, and equipment in the prosecution of work provided in the contract. The payment bond or other security accepted in lieu of a payment bond shall be in the amount of at least the total amount payable by the terms of the initial contract and shall be increased if requested by the governmental entity as the contract amount is increased.

§ 36-91-91. Liability of contracting party to subcontractors for noncompliance

If a payment bond or security deposit is not taken in the manner and form required in this article, the corporation or body for which work is done under the contract shall be liable to all subcontractors and to all persons furnishing labor, skill, tools, machinery, or materials to the contractor or subcontractor thereunder for any loss resulting to them from such failure. No agreement, modification, or change in the contract, change in the work covered by the contract, or extension of time for the completion of the contract shall release the sureties of such payment bond.

§ 36-91-92. Notice of commencement

(a) The contractor furnishing the payment bond or security deposit shall post on the public works construction site and file with the clerk of the superior court in the county in which the site is located a notice of commencement no later than 15 days after the contractor physically commences work on the project and supply a copy of the notice of commencement to any subcontractor, materialman, or person who makes a written request of the contractor. Failure to supply a copy of the notice of commencement within ten calendar days of receipt of the written request from the subcontractor, materialman, or person shall render the provisions of paragraph (1) of subsection (a) of Code Section 36-91-93 inapplicable to the subcontractor, materialman, or person making the request. The notice of commencement shall include:

(1) The name, address, and telephone number of the contractor;

(2) The name and location of the public work being constructed or a general description of the improvement;

(3) The name and address of the governmental entity that is contracting for the public works construction;

(4) The name and address of the surety for the performance and payment bonds, if any; and

(5) The name and address of the holder of the security deposit provided, if any.

(b) The failure to file a notice of commencement shall render the notice to contractor requirements of paragraph (2) of subsection (a) of Code Section 36-91-93 inapplicable.

(c) The clerk of the superior court shall file the notice of commencement within the records of that office and maintain an index separate from other real estate records or an index with the preliminary notices specified in subsection (a) of Code Section 44-14-361.3. Each such notice of commencement shall be indexed under the name of the governmental entity and the name of the contractor as contained in the notice of commencement.

§ 36-91-93. Rights of persons protected by payment bond or security deposit; governmental entity not a party

(a) Every person entitled to the protection of the payment bond or security deposit required to be given who has not been paid in full for labor or material furnished in the prosecution of the work referred to in such bond or security deposit before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by such person or the material or equipment or machinery was furnished or supplied by such person for which such claim is made, or when he or she has completed his or her subcontract for which claim is made, shall have the right to bring an action on such payment bond or security deposit for the amount, or the balance thereof, unpaid at the time of the commencement of such action and to prosecute such action to final execution and judgment for the sum or sums due such person; provided, however, that:

(1) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has not complied with the notice of commencement requirements shall have the right of action upon the payment bond or security deposit upon giving written notice to the contractor within 90 days from the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was performed or done. The notice to the contractor may be served by registered or certified mail, postage prepaid, or statutory overnight delivery, duly addressed to the contractor, at any place at which the contractor maintains an office or conducts his or her business or at his or her residence, by depositing such notice in any post office or branch post office or any letter box under the control of the United States Postal Service; alternatively, notice may be served in any manner in which the sheriffs of this state are authorized by law to serve summons or process; and

(2) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has complied with the notice of commencement requirements in accordance with subsection (a) of Code Section 36-91-92 shall have the right of action on the payment bond or security deposit, provided that such person shall, within 30 days from the filing of the notice of commencement or 30 days following the first delivery of labor, material, machinery, or equipment, whichever is later, give to the contractor a written notice setting forth:

(A) The name, address, and telephone number of the person providing labor, material, machinery, or equipment;

(B) The name and address of each person at whose instance the labor, material, machinery, or equipment is being furnished;

(C) The name and the location of the public works construction site; and

(D) A description of the labor, material, machinery, or equipment being provided and, if known, the contract price or anticipated value of the labor, material, machinery, or equipment to be provided or the amount claimed to be due, if any.

(b) Nothing contained in this Code section shall limit the right of action of a person entitled to the protection of the payment bond or security deposit required to be given pursuant to this article to the 90 day period following the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made.

(c) Every action instituted under this Code section shall be brought in the name of the claimant without making the governmental entity for which the work was done or was to be done a party to such action.

§ 36-91-94. Providing copy of bond or security deposit agreement

The official who has the custody of the bond or security deposit required by this article is authorized and directed to furnish to any person making application therefor a copy of the bond or security deposit agreement and the contract for which it was given, certified by the official who has custody of the bond or security deposit. With his or her application, such person shall also submit an affidavit that he or she has supplied labor or materials for such work and that payment therefor has not been made or that he or she is being sued on any such bond or security deposit. Such copy shall be primary evidence of the bond or security deposit and contract and shall be admitted in evidence without further proof. Applicants shall pay for such certified copies and such certified statements such fees as the official fixes to cover the cost of preparation thereof, provided that in no case shall the fee fixed exceed the fees which the clerks of the superior courts are permitted to charge for similar copies.

§ 36-91-95. Time limitation

No action can be instituted on the payment bonds or security deposits after one year from the completion of the contract and the acceptance of the public works construction by the proper public authorities. Every action instituted under this article shall be brought in the name of the claimant, without the governmental entity for which the work was done or was to be done being made a party thereto.

ARTICLE 5. PARTNERSHIP FOR PUBLIC FACILITIES AND INFRASTRUCTURE ACT

See below.

§ 36-91-110.

As used in this article, the term:
(1) ‘Comprehensive agreement’ means the written agreement between the private entity and the local government required by Code Section 36-91-115.
(2) ‘Develop’ or ‘development’ means to plan, design, develop, finance, lease, acquire, install, construct, operate, maintain, or expand.
(3) ‘Local authority’ means any local authority created pursuant to a local or general Act of the General Assembly, including a joint public instrumentality.
(4) ‘Local government’ means any county, municipality, consolidated government, or board of education.
(5) ‘Private entity’ means any natural person, corporation, general partnership, limited liability company, limited partnership, joint venture, business trust, public benefit corporation, nonprofit entity, or other business entity.
(6) ‘Qualifying project’ means any project selected in response to a request from a local government or submitted by a private entity as an unsolicited proposal in accordance with this article and subsequently reviewed and approved by a local government, within its sole discretion, as meeting a public purpose or public need. This term shall not include and shall have no application to any project involving:
(A) The generation of electric energy for sale pursuant to Chapter 3 of Title 46;
(B) Communications services pursuant to Articles 4 and 7 of Chapter 5 of Title 46;
(C) Cable and video services pursuant to Chapter 76 of this title; or
(D) Water reservoir projects as defined in paragraph (10) of Code Section 12-5-471, which shall be governed by Article 4 of this chapter.
(7) ‘Revenue’ means all revenues, income, earnings, user fees, lease payments, or other service payments arising out of or in connection with supporting the development or operation of a qualifying project.
(8) ‘Unsolicited proposal’ means a written proposal for a qualifying project that is received by a local government and is not in response to any request for proposal for a qualifying project issued by a local government.

§ 36-91-111.

(a) The Partnership for Public Facilities and Infrastructure Act Guidelines Committee is established to prepare model guidelines for local governments in the implementation of this article.
(b) The committee shall be composed of ten persons. Except for the local government officials or staff appointed to the committee, each committee member shall have subject matter expertise in architecture, construction management, engineering, finance, or real estate development. These appointments shall be made as follows:
(1) The following members shall be appointed by the Governor:
(A) One member or employee of a county governing authority;
(B) One member or employee of a municipal governing authority;
(C) One member or employee of a local board of education; and
(D) One licensed member of the State Bar of Georgia with expertise in representing local government in public works construction.
(2) The following members shall be appointed by the Speaker of the House of Representatives, provided that one of these appointees shall have expertise in working with local government:
(A) One member of the business community with expertise in construction management employed by a firm with less than $25 million in annual revenue;
(B) One member of the business community who is a licensed architect; and
(C) One member of the business community with expertise in real estate development; and
(3) The following members shall be appointed by the Lieutenant Governor, provided that one of these appointees shall have expertise in working with local government:
(A) One member of the business community with expertise in construction management employed by a firm with more than $25 million in annual revenue;
(B) One member of the business community who is a licensed professional engineer; and
(C) One member of the business community with expertise in finance.
(c) The terms of these committee appointments shall be for two years. At least three of these appointees shall reside outside of the metropolitan Atlanta area. The appointments shall be made as soon as feasible, but not later than August 1, 2015. The committee shall meet once a month or as needed and shall issue model guidelines to local governments no later than July 1, 2016. Such guidelines shall be updated every two years. The members of the committee shall elect a chairperson and a vice chairperson who shall serve for two-year terms in such office.
(d) Citizen members shall receive a daily expense allowance in the amount specified in subsection (b) of Code Section 45-7-21 as well as the mileage or transportation allowance authorized for state employees.
(e) Staff support shall be provided by the Department of Administrative Services, the Governor’s office, and the Office of Planning and Budget.

§ 36-91-112.

(a) Prior to executing any comprehensive agreement for the development or operation of a qualifying project pursuant to an unsolicited proposal received by a local government under this article, the local government shall adopt either:
(1) The model guidelines from the Partnership for Public Facilities and Infrastructure Act Guidelines Committee; or
(2) Its own guidelines as a policy, rule, regulation, or ordinance, which shall contain each of the factors identified in subsection (b) of this Code section.
(b) The model guidelines shall include, at a minimum, the following:
(1) The period of time each calendar year when the local government will consider receiving, processing, reviewing, or evaluating unsolicited proposals for qualifying projects, and such limited time period shall be established within the sole discretion of the local government;
(2) Procedures for the financial review and analysis of an unsolicited proposal that may include:
(A) A cost-benefit analysis;
(B) Evaluation of the public need for or benefit derived from the qualifying project;
(C) Evaluation of the estimated cost of the qualifying project for reasonableness in relation to similar facilities;
(D) Evaluation of the source of funding for the project;
(E) Consideration of plans to ensure timely development or operation;
(F) Evaluation of risk sharing, including cost or completion guarantees, added value, or debt or equity investments by the private entity; and
(G) Consideration of any increase in funding, dedicated revenue source, or other economic benefit that would not otherwise be available;
(3) Criteria for determining any fees authorized in Code Section 36-91-113 that the local government elects to charge the private entity for the processing, review, and evaluation of an unsolicited proposal;
(4) A requirement for the issuance of a request for proposals upon a decision by the local government to proceed with a qualifying project pursuant to an unsolicited proposal;
(5) Procedures for posting and publishing notice of the opportunity to offer competing proposals;
(6) Procedures for the processing, review, and consideration of competing proposals, and the period for the processing, review, and consideration of competing proposals shall not be less than 90 days;
(7) Procedures for determining whether information included in an unsolicited proposal shall be released as part of any request for proposals to ensure fair competition; and
(8) Procedures for identifying and appointing an independent owner adviser to the local government with expertise in architecture, engineering, or construction management to assist in the evaluation of an unsolicited proposal and to serve as owner adviser to the local government if the local government chooses to pursue any ensuing solicited bid process. The local government shall not be obligated to engage such services.

§ 36-91-113.

(a) If a local government adopts a rule, regulation, or ordinance affirming its participation in the process created in this article, a private entity may submit an unsolicited proposal for a project to the local government for review and determination as a qualifying project in accordance with the guidelines established by the local government. Any such unsolicited proposal shall be accompanied by the following material and information:
(1) A project description, including the location of the project, the conceptual design of such facility or facilities, and a conceptual plan for the provision of services or technology infrastructure;
(2) A feasibility statement that includes:
(A) The method by which the private entity proposes to secure any necessary property interests required for the project;
(B) A list of all permits and approvals required for the project from local, state, or federal agencies; and
(C) A list of public utility facilities, if any, that will be crossed by the project and a statement of the plans of the private entity to accommodate such crossings;
(3) A schedule for the initiation and completion of the project to include the proposed major responsibilities and timeline for activities to be performed by both the local government and private entity as well as a proposed schedule for obtaining the permits and approvals required in subparagraph (B) of paragraph (2) of this subsection;
(4) A financial plan setting forth the private entity’s general plans for financing the project, including the sources of the private entity’s funds and identification of any dedicated revenue source or proposed debt or equity investment on behalf of the private entity; a description of user fees, lease payments, and other service payments over the term of the comprehensive agreement pursuant to Code Section 36-91-115; and the methodology and circumstances for changes to such user fees, lease payments, and other service payments over time;
(5) A business case statement that shall include a basic description of any direct and indirect benefits that the private entity can provide in delivering the project, including relevant cost, quality, methodology, and process for identifying the project and time frame data;
(6) The names and addresses of the persons who may be contacted for further information concerning the unsolicited proposal; and
(7) Such additional material and information as the local government may reasonably request.
(b) For any unsolicited proposal of the development of a project received by a local government, the local government may charge and retain a reasonable fee to cover the costs of processing, reviewing, and evaluating the unsolicited proposal, including, without limitation, reasonable attorney’s fees and fees for financial, technical, and other necessary advisers or consultants.
(c) The local government may reject any proposal or unsolicited proposal at any time and shall not be required to provide a reason for its denial. If the local government rejects a proposal or unsolicited proposal submitted by a private entity, it shall have no obligation to return the proposal, unsolicited proposal, or any related materials following such rejection.
(d) A private entity assumes all risk in submission of a proposal or unsolicited proposal in accordance with subsections (a) and (b) of this Code section, and a local government shall not incur any obligation to reimburse a private entity for any costs, damages, or loss of intellectual property incurred by a private entity in the creation, development, or submission of a proposal or unsolicited proposal for a qualifying project.

§ 36-91-114.

(a) The local government may approve the project in an unsolicited proposal submitted by a private entity pursuant to Code Section 36-91-113 as a qualifying project. Determination by the local government of a qualifying project shall not bind the local government or the private entity to proceed with the qualifying project.
(b) Upon the local government’s determination of a qualifying project as provided in subsection (a) of this Code section, the local government shall:
(1) Seek competing proposals for the qualifying project by issuing a request for proposals for not less than 90 days; and
(2) Review all proposals submitted in response to the request for proposals based on the criteria established in the request for proposals.
(c) When the time for receiving proposals expires, the local government shall first rank the proposals in accordance with the factors set forth in the request for proposal or invitation for bids. The local government shall not be required to select the proposal with the lowest price offer, but it may consider price as one of various factors in evaluating the proposals received in response to the request for proposals for a qualifying project. Factors that may be considered include:
(1) The proposed cost of the qualifying project;
(2) The general reputation, industry experience, and financial capacity of the private entity;
(3) The proposed design of the qualifying project;
(4) The eligibility of the facility for accelerated selection, review, and documentation timelines under the local government’s guidelines;
(5) Benefits to the public;
(6) The private entity’s compliance with a minority business enterprise participation plan;
(7) The private entity’s plans to employ local contractors and residents; and
(8) Other criteria that the local government deems appropriate.
(d) After ranking the proposals, the local government shall begin negotiations with the first ranked private entity. If the local government and the first ranked private entity do not reach a comprehensive agreement or interim agreement, then the local government may conduct negotiations with the next ranked private entity. This process shall continue until the local government either voluntarily abandons the process or executes a comprehensive agreement or interim agreement with a private entity.
(e) At any time during the process outlined in this Code section but before the full execution of a comprehensive agreement, the local government may, without liability to any private entity or third party, cancel its request for proposals or reject all proposals received in response to its request for proposals, including the unsolicited proposal, for any reason whatsoever.
(f) Nothing in this article shall enlarge, diminish, or affect the authority, if any, otherwise possessed by the local government to take action that would impact the debt capacity of the State of Georgia or any local government. The credit of this state shall not be pledged or loaned to any private entity. The local government shall not loan money to the private entity in order to finance all or a portion of the qualifying project. A multiyear lease entered into by a local government which is not terminable at the end of each fiscal year during the term of the lease shall be considered a debt of the local government which enters into such lease, and such lease shall apply against the debt limitations of the local government.

§ 36-91-115.

(a) The comprehensive agreement entered into between the local government and the private entity selected in accordance with this article shall include:
(1) A thorough description of the duties of each party in the completion and operation of the qualifying project;
(2) Dates and schedules for the completion of the qualifying project;
(3) Any user fees, lease payments, or service payments as may be established by agreement of the parties, as well as any process for changing such fees or payments throughout the term of the agreement, and a copy of any service contract;
(4) Any reimbursements to be paid to the local government for services provided by the local government;
(5) A process for the review of plans and specifications for the qualifying project by the local government and approval by the local government if the plans and specifications conform to reasonable standards acceptable to the local government;
(6) A process for the periodic and final inspection of the qualifying project by the local government to ensure that the private entity’s activities are in accordance with the provisions of the comprehensive agreement;
(7) Delivery of performance and payment bonds in the amounts required in Code Sections 36-91-70 and 36-91-90 and in a form acceptable to the local government for those components of the qualifying project that involve construction, and surety bonds, letters of credit, or other forms of security acceptable to the local government for other phases and components of the development of the qualifying project;
(8) Submission of a policy or policies of public liability insurance, copies of which shall be filed with the local government accompanied by proofs of coverage, or self-insurance, each in form and amount satisfactory to the local government and reasonably sufficient to ensure coverage of tort liability to the public and employees and to enable the continued operation of the qualifying project;
(9) A process for monitoring the practices of the private entity by the local government to ensure that the qualifying project is properly maintained;
(10) The filing of appropriate financial statements to the local government on a periodic basis; and
(11) Provisions governing the rights and responsibilities of the local government and the private entity in the event that the comprehensive agreement is terminated or there is a material default by the private entity, including conditions governing assumption of the duties and responsibilities of the private entity by the local government and the transfer or purchase of property or other interests of the private entity by the local government, including provisions compliant with state constitutional limitations on public debt by the local government. Such policies and procedures shall be consistent with Code Section 36-91-116.
(b) The comprehensive agreement may include such other terms and conditions that the local government determines will serve the public purpose of this article and to which the private entity and the local government mutually agree, including, without limitation, provisions regarding unavoidable delays and provisions where the authority and duties of the private entity under this article shall cease and the qualifying project is dedicated to the local government for public use.
(c) Any changes in the terms of the comprehensive agreement, as may be agreed upon by the parties from time to time, shall be added to the comprehensive agreement by written amendment.
(d) The comprehensive agreement may provide for the development of phases or segments of the qualifying project.

§ 36-91-116.

(a) In the event of a material default by the private entity, the local government may terminate, with cause, the comprehensive agreement and exercise any other rights and remedies that may be available to it at law or in equity, including, but not limited to, claims under the maintenance, performance, or payment bonds; other forms of security; or letters of credit required by Code Section 36-91-115.
(b) The local government may elect to assume the responsibilities and duties of the private entity of the qualifying project, and in such case, it shall succeed to all of the right, title, and interest in such qualifying project subject to statutory limitations on the availability of future appropriated or otherwise unobligated funds.
(c) The power of eminent domain shall not be delegated to any private entity with respect to any project commenced or proposed pursuant to this article. Any local government having the power of condemnation under state law may exercise such power of condemnation to acquire the qualifying project in the event of a material default by the private entity. Any person who has perfected a security interest in the qualifying project may participate in the condemnation proceedings with the standing of a property owner.
(d) In the event the local government elects to take over a qualifying project pursuant to subsection (b) of this Code section, the local government may develop the qualifying project, impose user fees, and impose and collect lease payments for the use thereof.

36-91-117.

All power or authority granted by this article to public entities shall be in addition and supplemental to, and not in substitution for, the powers conferred by any other general, special, or local law. The limitations imposed by this article shall not affect the powers conferred by any other general, special, or local law and shall apply only to the extent that a local government elects to proceed under this article.

§ 36-91-118.

Nothing in this article shall be construed as or deemed a waiver of the sovereign or official immunity of any local government or any officer or employee thereof with respect to the participation in, or approval of, all or any part of the qualifying project or its operation, including, but not limited to, interconnection of the qualifying project with any other infrastructure or project.

§ 36-91-119.

(a) Local governments that proceed with procurement pursuant to competitive sealed bidding as defined in Code Section 36-91-2, or any other purchasing options available under current law, shall not be required to comply with this article.
(b) Nothing in this article shall apply to or affect the State Transportation Board, the Department of Transportation, or the State Road and Tollway Authority, or any project thereof.
(c) Nothing in this article shall abrogate the obligations of a local government or private entity to comply with the public meetings requirement in accordance with Chapter 14 of Title 50 or to disclose public information in accordance with Article 4 of Chapter 18 of Title 50.

Helping Thousands of Georgia Contractors Like You
With Bond Claims & Getting Paid