In researching liens in the Commonwealth of Virginia, I ran across a question that should be on the minds of construction professionals in Virginia, particularly suppliers of materials.  The question is simply “On an open account (based on a credit agreement or other arrangement), is each delivery to a particular contractor its own “work” such that the 90 day clock runs from the completion of each delivery, or do all deliveries to a particular project constitute the “work” on that project such that the 90 day clock only runs from the last delivery to the job site?” (How’s that for simple!)

Mechanics Lien Form Download

Get free mechanics lien form

We're the mechanics lien experts. We offer forms made by attorneys and trusted by thousands.

Download Free

The answer to this question is (drum roll please!)- “It depends.” (I know, you are shocked at such a “lawyerly” answer.)

The Virginia Supreme Court weighed in on this question in United Savings Association of Texas, F. S. B. v. Jim Carpenter Company, Record No. 951470 (2006).  The Jim Carpenter case involved three different cases of liens that were filed by materialmen pursuant to various forms of open account contracts.

You can read the case to see the particular facts of the case. But in essence, the owners/general contractors on the project argued that the material suppliers could not lien for any materials delivered to a particular project outside of the 90 day lien window. The material men argued that all of the materials were delivered to the same projects and therefore all constituted one continuous contract.

The Virginia Supreme Court held that the intent of the parties controls. On the one hand, general deliveries to a contractor for general use (i. e. warehousing for use at some time in the future) each constitute a separate contract, each with its own 90 day clock. On the other hand, if the material deliveries upon which the lien is based are all delivered for the benefit of a particular project then they all constitute one continuous contract and the 90 day clock does not start to run until the last delivery is completed.

Suppliers: Be careful with open accounts

What do you, as a construction professional, take from this case?  Be careful with your open accounts.  Make sure that when delivering materials to a job site based upon an open account you are exceedingly clear with your purchase order or takeoff language that certain materials are to be delivered to a certain project.  Failure to do so may lead a court to decide that the materials were a general delivery and cut off much or all of your recovery.

As with everything else to do with the picky issues with mechanics liens, all of the other requirements (150 day look back, notice, etc.) apply and good legal assistance is a must.

If you are interested in more thoughts on Virginia construction law, please check out my Construction Law Musings blog and join the conversation.

Summary
Article Name
Open Accounts and Mechanics Liens
Author
Publisher Name
Levelset
Publisher Logo
Was this article helpful?
You voted . Change your answer.