Private projects
A Notice of Contract must be filed after the contract is executed, and no later than the earliest of:
- 60 days after filing of the Notice of Substantial Completion
- 90 days after the filing of the Notice of Termination
- 90 days after last furnishing labor or materials to the project
Notice cannot be sent late, and must be filed with the register of deeds.