Private projects
General contractors and all other parties who are contracted directly with the property owner are not required to send preliminary notice on private projects.
General contractors and all other parties who are contracted directly with the property owner are not required to send preliminary notice on private projects.
General contractors are not required to send notice on public projects.
Since GCs will not make a claim against their own bond for non-payment, they do not have bond claim rights, and have no preliminary notice requirement.
Subcontractors and suppliers must send a notice of lien rights on private projects.
Notice of Lien Rights must served on owner within 20 days of first delivering materials or labor and filed with recorder within 5 days of delivery to owner (unless one of the exceptions apply). If the project is not owner-occupied residential and is funded by a lender, the deadline is increased to 45 days.
2nd-tier subcontractors and suppliers must send preliminary notice on public projects.
Notice is not specifically required from 1st-tier subs, but it might be best practice to provide anyway.
It depends. A preliminary notice is required in Montana, but certain potential lien claimants are excepted from the notice requirement. Despite the fact that some lien claimants are not required to give preliminary notice, it may be advisable to send notice anyway, as Montana courts have not provided sufficient guidance as to the meaning, scope, and application of the exceptions.
Notwithstanding the foregoing, the following parties are not required to send and file preliminary notice in Montana: 1) a party who furnished labor or material directly to the property owner at the owner’s request; 2) wage laborers; 3) a party who furnishes labor or material to a residential project for five or more families; 4) a party who furnishes labor or material to a project that is partially or wholly commercial in character.
Preliminary notice must be served on the property owner not later than 20 or 45 days after first furnishing of labor or materials to the project. The 20-day period applies to all projects other than a non-owner-occupied residence where payment is made by a lender with a security interest in the property.
Further, the preliminary notice must be filed with the clerk and recorder of the county in which the property is located. The notice must be filed within 5 days after notice was given to the owner.
If the preliminary notice is sent late, all is not lost. If given after the 20- or 45-day period, the notice only covers work or materials furnished within the 20 or 45 days preceding the notice.
However, if the preliminary notice is required, it is a prerequisite to filing a valid mechanics lien. In that case, the preliminary notice must be filed with the clerk and recorder of the county in which the property is located prior to filing the mechanics lien.
The preliminary notice should be served on the property owner either by personal service, or by certified mail, return receipt requested. If served on the property owner personally, a written acknowledgement of receipt from the property owner is required.
The notice must also be filed with the clerk and recorder of the county in which the property is located.
Yes. The preliminary notice must also be filed with the clerk and recorder of the county in which the property is located. The lien claimant should also be careful to send the notice to all property owners of record.
In Montana, the notice is considered delivered when sent – if sent by certified mail, return receipt requested. If the notice is given by personal delivery, it is considered delivered when the property owner signs the written acknowledgment of receipt.
It depends. All parties supplying materials or supplies to any subcontractor (or anybody other than the pubic entity or GC) must deliver preliminary notice to the general contractor to preserve rights to make a bond claim upon no-payment.
In order to retain rights to make a claim on the bond, a 2nd-tier or lower subcontractor or supplier must deliver the preliminary notice within 30 days of first delivery of materials or supplies.
Failure to timely send the preliminary notice when required is fatal to a subsequent bond claim.
When required preliminary notice should be sent by certified mail.
Notice must be provided to the GC.
In Montana, if a Notice of Right to Lien has been filed, and the claimant has been paid in full for the labor and/or materials related to the project, then a release of the notice may be filed in the same clerk and recorder's office where the notice was filed.
This notice release is governed by Mont. Code §71-3-538, and should include the following information release should include the recording number of the notice, the date the notice was filed, and the name of the party who recorded the notice.
Montana’s preliminary notice rules and requirements are complex, and not well or clearly defined by statute or the courts. While requiring preliminary notice is the default in Montana, the exceptions to the requirement nearly consume the requirement that preliminary notice be sent. The parties that appear to be specifically exempted from the preliminary notice requirement by statute are:
When these exceptions are peeled away, it appears that the only parties technically required to send preliminary notice in Montana are: parties, other than direct contractors or laborers, working on completely residential projects on dwellings of less than 5 families.
Notwithstanding the foregoing, however, it is likely advisable to send preliminary notice anyway on most projects, just to be safe. There is little jurisprudence providing guidance on these issues, and other sections of Montana law seem to contemplate notices being required in other circumstances.
One of the circumstances that clouds the water with respect to preliminary notice requirements is the statutory section setting forth the calculation of the deadlines related to Montana preliminary notices. Montana law provides a preliminary notice deadline of either 20 or 45 days after first furnishing labor or materials to the project. The base deadline is 20 days, which applies in all circumstances other than those that give rise to the specific 45-day deadline. The 45-day deadline applies
“when payment for services or materials furnished pursuant to a real estate improvement contract, excluding a contract on an owner-occupied residence, is made by or on behalf of the contracting owner from funds provided by a regulated lender and secured by an interest, lien, mortgage, or encumbrance for the purpose of paying the particular real estate improvement being liened.”
So, breaking that down a little, the 45 day deadline applies to projects: 1) other than an owner-occupied residence; where 2) payment is made by a lender with a security interest in the property. Since, it appears from the exceptions above that notice is only required from some participants on residential projects of less than 5 “units” it appears the 45-day deadline would only apply to residential projects which are not the owner’s residence and are funded by a lender. And, accordingly, the 20-day deadline would apply to owner-occupied residential projects, and other residential projects that are not being funded by a lender.
Montana has another interesting rule regarding preliminary notices, as well. After the notice is sent (either by certified mail or personally delivered), it must also be filed with the county’s clerk and recorder within 5 days. Few states require the recordation of preliminary notices, but Montana is one of them. Even more rare, Montana specifically requires that, if a participant is paid after filing the preliminary notice, a release of notice must be recorded. Generally, since notices are usually not recorded, and do not encumber the property (since they are not liens themselves), there is no need to “release” them. However, Montana specifically requires that notices be released within 5 days of request from the owner if payment for the labor or materials subject of the notice has been made.
Finally, Montana allows a subcontractor who has not been paid to make a written request on the property owner to be notified when the property owner makes any subsequent payments. If this request is made, the owner must inform the sub of any progress or final payment made to the GC. There is, however, very little information related to this notice in the statute, however, as there is no specific time period, content, or delivery requirements outlined by Montana law.
The first step is to download a free copy of the Montana notice of right to claim lien form. Since Montana has specific requirements for the language and formatting for preliminary notices, our forms are written by construction attorneys to make this part easy for you to get right.
See all construction notices and forms available in Montana here
Take extra care to make sure the information you include on your preliminary notice is correct. That’s because making a mistake when preparing your notice could eliminate your right to file a Missouri mechanics lien if you’re left unpaid down the line. Double check everything and make sure it’s accurate.
You should serve your notice on the property owner either by personal service, or by certified mail, return receipt requested. If served on the property owner personally, a written acknowledgement of receipt from the property owner is required.
Additionally, Montana notices need to be filed in with the clerk in the county where the property is located.
Select Preliminary Notice document.
Provide basic job information.
Levelset sends the document for you. Postage included!