Tennessee Retainage Requirements
- Private Jobs
- Public Jobs
- Top Links
5% Retainage Limit
Retainage cannot exceed 5%.
90 Day Pay Period
The owner must release retainage to the original contractor within 90 days from substantial completion. Contractors must release retainage to their subcontractors within 10 days of the owner releasing retainage to the contractor.
There's No Process to Recover
Not specified
Held In Escrow
In Tennessee, if the original contract is valued at $500K or more, retained funds must be deposited in a separate escrow account.
5 Percent
Retainage cannot exceed 5%.
90 Day Pay Period
Retainage must be released to the original contractor within 90 days of substantial completion. Upon receipt of retainage, contractor must release retainage to subcontractors within 10 days.
There's No Process to Recover
Not specified
Held In Escrow
In Tennessee, if the original contract is valued at $500K or more, retained funds must be deposited in a separate escrow account.
Retainage, also called “retention,” is an amount of money “held back” from a contractor or subcontractor during the course of a construction project. In general, retainage serves two main purposes:
- To provide an incentive to the contractor or subcontractor to complete the project; &
- To give the owner some protection against problems like liens, contractual defaults, delays, and more.
In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and answers to frequently asked questions about Tennessee’s retainage requirements.
Tennessee’s retainage limits and deadlines
The same general rules apply to all private and public projects in Tennessee when it comes to retainage. The amount of retainage that can be withheld on Tennessee construction projects is limited to no more than 5% of the contract amount. Furthermore, if the original contract is valued at $500K or more, the amount withheld must be deposited in an interest-bearing escrow account. Failure to do so can make the party liable for a statutory penalty of $300 per day.
As far as the timing of the release of retainage. Property owners/public entities are required to release retainage to the prime contractor within 90 days of completion of the work, or 90 days of substantial completion; whichever occurs first. Once received subcontractors and suppliers must release retainage down the contracting chain within 10 days of receipt.